Rural Electrification - Peninsula District
Project Code: PRJ-000495
Project Progress
86%
Fund Allocated
₹19.7 Cr
FY 2026-27
Funds Used
₹9.2 Cr
47% utilized
People Reached
1,006
3,556 person-days
About This Project
Rural Electrification implemented in Peninsula District under Fisheries Development Phase 5. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.
Objectives
- Improve last-mile connectivity and access to essential services
- Ensure transparent fund utilization with geo-tagged progress monitoring
- Generate local employment and livelihood opportunities
- Strengthen community infrastructure for long-term development
Key Details
Category
Education
Implementing Agency
District Rural Development Agency
Sanction Order
WODC/SAN/202627/0495
Timeline
01 Aug 2024 – 01 Mar 2027
Project Timeline
01 Aug 2024
Project Sanctioned
Administrative sanction issued under Fisheries Development Phase 5
01 Aug 2024
GPS Tagging Completed
Project site coordinates captured and verified on mobile app
07 Sept 2026
Fund Release — Phase 1
69% of allocated funds released after geo-tag validation
07 Sept 2026
Latest Progress Update
Physical progress at 86%; fund utilization at 47%