Western Odisha Development Council (WODC) — Integrated Project & Fund Management System
Back to Projects

Rural Electrification - Border District

On Hold
GPS Verified

Project Code: PRJ-000455

Handlooms & TextilesBorder District, Border District Block 1Phase: Civil Works

Project Progress

47%

47% complete

Fund Allocated

₹37.7 Cr

FY 2025-26

Funds Used

₹15.1 Cr

40% complete

40% utilized

People Reached

4,810

5,077 person-days

About This Project

Rural Electrification implemented in Border District under Sanitation Mission Phase 5. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.

Objectives

  • Improve last-mile connectivity and access to essential services
  • Ensure transparent fund utilization with geo-tagged progress monitoring
  • Generate local employment and livelihood opportunities

Key Details

Category

Infrastructure

Implementing Agency

District Rural Development Agency

Sanction Order

WODC/SAN/202526/0455

Timeline

01 Sept 202401 May 2027

Project Timeline

  1. 01 Sept 2024

    Project Sanctioned

    Administrative sanction issued under Sanitation Mission Phase 5

  2. 01 Sept 2024

    GPS Tagging Completed

    Project site coordinates captured and verified on mobile app

  3. 01 Sept 2026

    Fund Release — Phase 1

    65% of allocated funds released after geo-tag validation

  4. 01 Sept 2026

    Latest Progress Update

    Physical progress at 47%; fund utilization at 40%

Rural Electrification - Border District | Western Odisha Development Council (WODC)