Western Odisha Development Council (WODC) — Integrated Project & Fund Management System
Back to Projects

Bridge Construction Project - Forest District

In Progress
GPS Verified

Project Code: PRJ-000409

CultureForest District, Forest District Block 5Phase: Equipment & Finishing

Project Progress

85%

85% complete

Fund Allocated

₹46.9 Cr

FY 2026-27

Funds Used

₹21.8 Cr

46% complete

46% utilized

People Reached

44,126

20,804 person-days

About This Project

Bridge Construction Project implemented in Forest District under Safe Drinking Water Programme Phase 5. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.

Objectives

  • Improve last-mile connectivity and access to essential services
  • Ensure transparent fund utilization with geo-tagged progress monitoring
  • Generate local employment and livelihood opportunities
  • Strengthen community infrastructure for long-term development

Key Details

Category

Social Welfare

Implementing Agency

District Rural Development Agency

Sanction Order

WODC/SAN/202627/0409

Timeline

01 Nov 202401 Sept 2027

Project Timeline

  1. 01 Nov 2024

    Project Sanctioned

    Administrative sanction issued under Safe Drinking Water Programme Phase 5

  2. 01 Nov 2024

    GPS Tagging Completed

    Project site coordinates captured and verified on mobile app

  3. 01 Sept 2026

    Fund Release — Phase 1

    71% of allocated funds released after geo-tag validation

  4. 01 Sept 2026

    Latest Progress Update

    Physical progress at 85%; fund utilization at 46%

Bridge Construction Project - Forest District | Western Odisha Development Council (WODC)