School Building Construction - Reservoir District
Project Code: PRJ-000384
Project Progress
100%
Fund Allocated
₹3 Cr
FY 2023-24
Funds Used
₹71.8 L
24% utilized
People Reached
17,029
9,965 person-days
About This Project
School Building Construction implemented in Reservoir District under Fisheries Development Phase 5. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.
Objectives
- Improve last-mile connectivity and access to essential services
- Ensure transparent fund utilization with geo-tagged progress monitoring
- Generate local employment and livelihood opportunities
- Strengthen community infrastructure for long-term development
Key Details
Category
Education
Implementing Agency
District Rural Development Agency
Sanction Order
WODC/SAN/202324/0384
Timeline
01 Mar 2024 – 01 Apr 2026
Project Timeline
01 Mar 2024
Project Sanctioned
Administrative sanction issued under Fisheries Development Phase 5
01 Mar 2024
GPS Tagging Completed
Project site coordinates captured and verified on mobile app
02 Sept 2026
Fund Release — Phase 1
50% of allocated funds released after geo-tag validation
02 Sept 2026
Latest Progress Update
Physical progress at 100%; fund utilization at 24%
01 Apr 2026
Project Completed
Final inspection passed; project commissioned and handed over