Playground Development - Hill District
Project Code: PRJ-000358
Project Progress
76%
Fund Allocated
₹3 Cr
FY 2026-27
Funds Used
₹65.5 L
22% utilized
People Reached
31,317
15,680 person-days
About This Project
Playground Development implemented in Hill District under Nutrition Security Programme Phase 5. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.
Objectives
- Improve last-mile connectivity and access to essential services
- Ensure transparent fund utilization with geo-tagged progress monitoring
- Generate local employment and livelihood opportunities
- Strengthen community infrastructure for long-term development
Key Details
Category
Infrastructure
Implementing Agency
District Rural Development Agency
Sanction Order
WODC/SAN/202627/0358
Timeline
01 Nov 2024 – 01 Nov 2027
Project Timeline
01 Nov 2024
Project Sanctioned
Administrative sanction issued under Nutrition Security Programme Phase 5
01 Nov 2024
GPS Tagging Completed
Project site coordinates captured and verified on mobile app
01 Sept 2026
Fund Release — Phase 1
48% of allocated funds released after geo-tag validation
01 Sept 2026
Latest Progress Update
Physical progress at 76%; fund utilization at 22%