Skip to main content
Western Odisha Development Council (WODC) — Integrated Project & Fund Management System
Back to Projects

Primary Health Centre Construction - Canyon District

Completed
GPS Verified

Project Code: PRJ-000342

Labour & EmploymentCanyon District, Canyon District Block 4Phase: Commissioning & Handover

Project Progress

100%

100% complete

Fund Allocated

₹24 Cr

FY 2024-25

Funds Used

₹6.7 Cr

28% complete

28% utilized

People Reached

21,273

11,662 person-days

About This Project

Primary Health Centre Construction implemented in Canyon District under Skill Development Mission. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.

Objectives

  • Improve last-mile connectivity and access to essential services
  • Ensure transparent fund utilization with geo-tagged progress monitoring
  • Generate local employment and livelihood opportunities
  • Strengthen community infrastructure for long-term development

Key Details

Category

Social Welfare

Implementing Agency

District Rural Development Agency

Sanction Order

WODC/SAN/202425/0342

Timeline

01 Oct 202401 Aug 2027

Project Timeline

  1. 01 Oct 2024

    Project Sanctioned

    Administrative sanction issued under Skill Development Mission

  2. 01 Oct 2024

    GPS Tagging Completed

    Project site coordinates captured and verified on mobile app

  3. 08 Sept 2026

    Fund Release — Phase 1

    57% of allocated funds released after geo-tag validation

  4. 08 Sept 2026

    Latest Progress Update

    Physical progress at 100%; fund utilization at 28%

  5. 01 Aug 2027

    Project Completed

    Final inspection passed; project commissioned and handed over