Piped Water Supply - Fishery District
Project Code: PRJ-000336
Project Progress
19%
Fund Allocated
₹37.4 Cr
FY 2025-26
Funds Used
₹14 Cr
37% utilized
People Reached
10,350
7,293 person-days
About This Project
Piped Water Supply implemented in Fishery District under Tribal Development Programme Phase 5. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.
Objectives
- Improve last-mile connectivity and access to essential services
- Ensure transparent fund utilization with geo-tagged progress monitoring
- Generate local employment and livelihood opportunities
Key Details
Category
Health
Implementing Agency
District Rural Development Agency
Sanction Order
WODC/SAN/202526/0336
Timeline
01 Mar 2025 – 01 Jan 2026
Project Timeline
01 Mar 2025
Project Sanctioned
Administrative sanction issued under Tribal Development Programme Phase 5
01 Mar 2025
GPS Tagging Completed
Project site coordinates captured and verified on mobile app
03 Sept 2026
Fund Release — Phase 1
75% of allocated funds released after geo-tag validation
03 Sept 2026
Latest Progress Update
Physical progress at 19%; fund utilization at 37%