Irrigation Canal Project - Canyon District

Delayed
GPS Verified

Project Code: PRJ-000325

Sports & Youth ServicesCanyon District, Canyon District Block 5Phase: Commissioning & Handover

Project Progress

90%

90% complete

Fund Allocated

₹11.4 Cr

FY 2023-24

Funds Used

₹2.9 Cr

26% complete

26% utilized

People Reached

21,622

11,802 person-days

About This Project

Irrigation Canal Project implemented in Canyon District under Livelihood Support Programme Phase 5. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.

Objectives

  • Improve last-mile connectivity and access to essential services
  • Ensure transparent fund utilization with geo-tagged progress monitoring
  • Generate local employment and livelihood opportunities
  • Strengthen community infrastructure for long-term development

Key Details

Category

Infrastructure

Implementing Agency

District Rural Development Agency

Sanction Order

WODC/SAN/202324/0325

Timeline

01 May 202501 Dec 2026

Project Timeline

  1. 01 May 2025

    Project Sanctioned

    Administrative sanction issued under Livelihood Support Programme Phase 5

  2. 01 May 2025

    GPS Tagging Completed

    Project site coordinates captured and verified on mobile app

  3. 04 Sept 2026

    Fund Release — Phase 1

    41% of allocated funds released after geo-tag validation

  4. 04 Sept 2026

    Latest Progress Update

    Physical progress at 90%; fund utilization at 26%

Irrigation Canal Project - Canyon District | Western Odisha Development Council (WODC)