Skip to main content
Western Odisha Development Council (WODC) — Integrated Project & Fund Management System
Back to Projects

Drainage System Improvement - Agricultural District

In Progress
GPS Verified

Project Code: PRJ-000291

Water ResourcesAgricultural District, Agricultural District Block 4Phase: Civil Works

Project Progress

36%

36% complete

Fund Allocated

₹6.8 Cr

FY 2023-24

Funds Used

₹2.7 Cr

39% complete

39% utilized

People Reached

597

3,392 person-days

About This Project

Drainage System Improvement implemented in Agricultural District under Handloom Promotion Scheme Phase 2. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.

Objectives

  • Improve last-mile connectivity and access to essential services
  • Ensure transparent fund utilization with geo-tagged progress monitoring
  • Generate local employment and livelihood opportunities

Key Details

Category

Livelihood

Implementing Agency

District Rural Development Agency

Sanction Order

WODC/SAN/202324/0291

Timeline

01 Dec 202501 Oct 2026

Project Timeline

  1. 01 Dec 2025

    Project Sanctioned

    Administrative sanction issued under Handloom Promotion Scheme Phase 2

  2. 01 Dec 2025

    GPS Tagging Completed

    Project site coordinates captured and verified on mobile app

  3. 03 Sept 2026

    Fund Release — Phase 1

    73% of allocated funds released after geo-tag validation

  4. 03 Sept 2026

    Latest Progress Update

    Physical progress at 36%; fund utilization at 39%

Drainage System Improvement - Agricultural District | Western Odisha Development Council (WODC)