Drainage System Improvement - Urban District

Delayed
GPS Verified

Project Code: PRJ-000251

Water ResourcesUrban District, Urban District Block 1Phase: Ground Preparation

Project Progress

30%

30% complete

Fund Allocated

₹8.8 Cr

FY 2023-24

Funds Used

₹2.2 Cr

25% complete

25% utilized

People Reached

49,669

23,021 person-days

About This Project

Drainage System Improvement implemented in Urban District under Skill Development Mission Phase 3. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.

Objectives

  • Improve last-mile connectivity and access to essential services
  • Ensure transparent fund utilization with geo-tagged progress monitoring
  • Generate local employment and livelihood opportunities

Key Details

Category

Social Welfare

Implementing Agency

District Rural Development Agency

Sanction Order

WODC/SAN/202324/0251

Timeline

01 Mar 202501 Dec 2026

Project Timeline

  1. 01 Mar 2025

    Project Sanctioned

    Administrative sanction issued under Skill Development Mission Phase 3

  2. 01 Mar 2025

    GPS Tagging Completed

    Project site coordinates captured and verified on mobile app

  3. 08 Sept 2026

    Fund Release — Phase 1

    41% of allocated funds released after geo-tag validation

  4. 08 Sept 2026

    Latest Progress Update

    Physical progress at 30%; fund utilization at 25%