Rural Water Supply Scheme - Canal District
Project Code: PRJ-000221
Project Progress
64%
Fund Allocated
₹12.2 Cr
FY 2026-27
Funds Used
₹3.3 Cr
27% utilized
People Reached
15,415
9,319 person-days
About This Project
Rural Water Supply Scheme implemented in Canal District under Housing for All Scheme Phase 2. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.
Objectives
- Improve last-mile connectivity and access to essential services
- Ensure transparent fund utilization with geo-tagged progress monitoring
- Generate local employment and livelihood opportunities
- Strengthen community infrastructure for long-term development
Key Details
Category
Energy
Implementing Agency
District Rural Development Agency
Sanction Order
WODC/SAN/202627/0221
Timeline
01 Sept 2025 – 01 Aug 2027
Project Timeline
01 Sept 2025
Project Sanctioned
Administrative sanction issued under Housing for All Scheme Phase 2
01 Sept 2025
GPS Tagging Completed
Project site coordinates captured and verified on mobile app
06 Sept 2026
Fund Release — Phase 1
60% of allocated funds released after geo-tag validation
06 Sept 2026
Latest Progress Update
Physical progress at 64%; fund utilization at 27%