Village Road Development - Orchard District
Project Code: PRJ-000163
Project Progress
77%
Fund Allocated
₹37 Cr
FY 2023-24
Funds Used
₹21.1 Cr
57% utilized
People Reached
23,463
12,538 person-days
About This Project
Village Road Development implemented in Orchard District under Forest Conservation Scheme Phase 3. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.
Objectives
- Improve last-mile connectivity and access to essential services
- Ensure transparent fund utilization with geo-tagged progress monitoring
- Generate local employment and livelihood opportunities
- Strengthen community infrastructure for long-term development
Key Details
Category
Infrastructure
Implementing Agency
District Rural Development Agency
Sanction Order
WODC/SAN/202324/0163
Timeline
01 Jun 2025 – 01 Jul 2027
Project Timeline
01 Jun 2025
Project Sanctioned
Administrative sanction issued under Forest Conservation Scheme Phase 3
01 Jun 2025
GPS Tagging Completed
Project site coordinates captured and verified on mobile app
08 Sept 2026
Fund Release — Phase 1
74% of allocated funds released after geo-tag validation
08 Sept 2026
Latest Progress Update
Physical progress at 77%; fund utilization at 57%