Western Odisha Development Council (WODC) — Integrated Project & Fund Management System
Back to Projects

Irrigation Canal Project - Spring District

Delayed
GPS Verified

Project Code: PRJ-000145

IndustriesSpring District, Spring District Block 2Phase: Civil Works

Project Progress

45%

45% complete

Fund Allocated

₹46.1 Cr

FY 2025-26

Funds Used

₹17.9 Cr

39% complete

39% utilized

People Reached

26,764

13,859 person-days

About This Project

Irrigation Canal Project implemented in Spring District under Skill Development Mission Phase 2. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.

Objectives

  • Improve last-mile connectivity and access to essential services
  • Ensure transparent fund utilization with geo-tagged progress monitoring
  • Generate local employment and livelihood opportunities

Key Details

Category

Agriculture

Implementing Agency

District Rural Development Agency

Sanction Order

WODC/SAN/202526/0145

Timeline

01 Nov 202501 Mar 2026

Project Timeline

  1. 01 Nov 2025

    Project Sanctioned

    Administrative sanction issued under Skill Development Mission Phase 2

  2. 01 Nov 2025

    GPS Tagging Completed

    Project site coordinates captured and verified on mobile app

  3. 04 Sept 2026

    Fund Release — Phase 1

    57% of allocated funds released after geo-tag validation

  4. 04 Sept 2026

    Latest Progress Update

    Physical progress at 45%; fund utilization at 39%