Skip to main content
Western Odisha Development Council (WODC) — Integrated Project & Fund Management System
Back to Projects

Bridge Construction Project - Green District

Planned
Pending Verification

Project Code: PRJ-000089

TransportGreen District, Green District Block 3Phase: Administrative Sanction

Project Progress

0%

0% complete

Fund Allocated

₹24.8 Cr

FY 2024-25

Funds Used

₹10.1 Cr

41% complete

41% utilized

People Reached

23,028

12,364 person-days

About This Project

Bridge Construction Project implemented in Green District under Climate Resilience Programme Phase 3. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.

Objectives

  • Improve last-mile connectivity and access to essential services
  • Ensure transparent fund utilization with geo-tagged progress monitoring
  • Generate local employment and livelihood opportunities

Key Details

Category

Housing

Implementing Agency

District Rural Development Agency

Sanction Order

WODC/SAN/202425/0089

Timeline

01 Dec 202501 Dec 2027

Project Timeline

  1. 01 Dec 2025

    Project Sanctioned

    Administrative sanction issued under Climate Resilience Programme Phase 3

  2. 01 Dec 2025

    GPS Tagging Completed

    Project site coordinates captured and verified on mobile app

  3. 03 Sept 2026

    Fund Release — Phase 1

    53% of allocated funds released after geo-tag validation

  4. 03 Sept 2026

    Latest Progress Update

    Physical progress at 0%; fund utilization at 41%