Community Hall Construction - Forest District
Project Code: PRJ-000086
Project Progress
23%
Fund Allocated
₹41.3 Cr
FY 2026-27
Funds Used
₹15.9 Cr
39% utilized
People Reached
1,983
3,946 person-days
About This Project
Community Hall Construction implemented in Forest District under Tribal Development Programme. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.
Objectives
- Improve last-mile connectivity and access to essential services
- Ensure transparent fund utilization with geo-tagged progress monitoring
- Generate local employment and livelihood opportunities
Key Details
Category
Social Welfare
Implementing Agency
District Rural Development Agency
Sanction Order
WODC/SAN/202627/0086
Timeline
01 Jul 2025 – 01 Nov 2026
Project Timeline
01 Jul 2025
Project Sanctioned
Administrative sanction issued under Tribal Development Programme
01 Jul 2025
GPS Tagging Completed
Project site coordinates captured and verified on mobile app
04 Sept 2026
Fund Release — Phase 1
58% of allocated funds released after geo-tag validation
04 Sept 2026
Latest Progress Update
Physical progress at 23%; fund utilization at 39%