Irrigation Canal Project - Plateau District

Delayed
Manually Entered

Project Code: PRJ-000065

IndustriesPlateau District, Plateau District Block 1Phase: Administrative Sanction

Project Progress

12%

12% complete

Fund Allocated

₹27.6 Cr

FY 2024-25

Funds Used

₹11.6 Cr

42% complete

42% utilized

People Reached

38,363

18,498 person-days

About This Project

Irrigation Canal Project implemented in Plateau District under Women Empowerment Mission. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.

Objectives

  • Improve last-mile connectivity and access to essential services
  • Ensure transparent fund utilization with geo-tagged progress monitoring
  • Generate local employment and livelihood opportunities

Key Details

Category

Urban Development

Implementing Agency

District Rural Development Agency

Sanction Order

WODC/SAN/202425/0065

Timeline

01 Apr 202401 Jan 2027

Project Timeline

  1. 01 Apr 2024

    Project Sanctioned

    Administrative sanction issued under Women Empowerment Mission

  2. 01 Apr 2024

    GPS Tagging Completed

    Project site coordinates captured and verified on mobile app

  3. 02 Sept 2026

    Fund Release — Phase 1

    58% of allocated funds released after geo-tag validation

  4. 02 Sept 2026

    Latest Progress Update

    Physical progress at 12%; fund utilization at 42%

Irrigation Canal Project - Plateau District | Western Odisha Development Council (WODC)