Western Odisha Development Council (WODC) — Integrated Project & Fund Management System
Back to Projects

Rural Electrification - Coastal District

In Progress
GPS Verified

Project Code: PRJ-000055

IT & ElectronicsCoastal District, Coastal District Block 3Phase: Civil Works

Project Progress

46%

46% complete

Fund Allocated

₹16.4 Cr

FY 2024-25

Funds Used

₹4.5 Cr

28% complete

28% utilized

People Reached

14,079

8,785 person-days

About This Project

Rural Electrification implemented in Coastal District under Climate Resilience Programme Phase 3. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.

Objectives

  • Improve last-mile connectivity and access to essential services
  • Ensure transparent fund utilization with geo-tagged progress monitoring
  • Generate local employment and livelihood opportunities

Key Details

Category

Agriculture

Implementing Agency

District Rural Development Agency

Sanction Order

WODC/SAN/202425/0055

Timeline

01 Sept 202401 Apr 2026

Project Timeline

  1. 01 Sept 2024

    Project Sanctioned

    Administrative sanction issued under Climate Resilience Programme Phase 3

  2. 01 Sept 2024

    GPS Tagging Completed

    Project site coordinates captured and verified on mobile app

  3. 06 Sept 2026

    Fund Release — Phase 1

    41% of allocated funds released after geo-tag validation

  4. 06 Sept 2026

    Latest Progress Update

    Physical progress at 46%; fund utilization at 28%

Rural Electrification - Coastal District | Western Odisha Development Council (WODC)