Community Hall Construction - Plain District
Project Code: PRJ-000026
Project Progress
100%
Fund Allocated
₹42.8 Cr
FY 2024-25
Funds Used
₹15.5 Cr
36% utilized
People Reached
48,008
22,356 person-days
About This Project
Community Hall Construction implemented in Plain District under Forest Conservation Scheme. This project aims to improve public services and infrastructure for local communities through transparent fund utilization, geo-tagged monitoring, and beneficiary-focused delivery.
Objectives
- Improve last-mile connectivity and access to essential services
- Ensure transparent fund utilization with geo-tagged progress monitoring
- Generate local employment and livelihood opportunities
- Strengthen community infrastructure for long-term development
Key Details
Category
Energy
Implementing Agency
District Rural Development Agency
Sanction Order
WODC/SAN/202425/0026
Timeline
01 Apr 2024 – 01 Nov 2026
Project Timeline
01 Apr 2024
Project Sanctioned
Administrative sanction issued under Forest Conservation Scheme
01 Apr 2024
GPS Tagging Completed
Project site coordinates captured and verified on mobile app
05 Sept 2026
Fund Release — Phase 1
51% of allocated funds released after geo-tag validation
05 Sept 2026
Latest Progress Update
Physical progress at 100%; fund utilization at 36%
01 Nov 2026
Project Completed
Final inspection passed; project commissioned and handed over